スペインの2002年ー2009年のMadrid-Barcelona の621kmの高速鉄道(AVE)建設で、工事予算は7'550'000'000ユーロ(75億5000万ユーロ)で、6'822'000'000ユーロ(68億2200万ユーロ)で落札され、結局8'996'000'000ユーロ(89億6600万ユーロ)に。建設中に工事内容を変更し建設費用を増大させる。(意図的に工事費用をわざと安く見つもりして、工事が始まると工事費用をわざと引き上げる 悪質なスペインの公共工事の建設会社の手口。)
INFORME DEL TRIBUNAL DE CUENTAS SOBRE EL AVE MADRID-BARCELONA
La obra del AVE a Barcelona se adjudicó en 6.800 millones y al final costó 9.000
Los 621 kilómetros se asignaron con una baja del 9% pero se facturó un 31% más
“Numerosas modificaciones no cumplen los requisitos legales”, se afirma en el informe
Nueve detenidos por inflar las obras de AVE a Barcelona en 6 millones
FOTOGALERÍA Detenciones por las obras del AVE en Barcelona
Varapalo del auditor
El País Madrid 5 MAY 2014 - 22:46 CET
++++++++++++++++++++++++++++++++++++++++++++++++++++++
COURT OF AUDITORS REPORT ON AVE MADRID-BARCELONA
The work of the AVE to Barcelona was awarded 6,800 million and eventually cost 9,000
The 621 miles were assigned with a 9% but turnover up 31%
"Numerous modifications do not meet the legal requirements," the report states
Nine arrested for inflating works AVE to Barcelona 6 million
PHOTOGALLERY Arrests TGV works in Barcelona
Setback auditor
The Country Madrid 5 MAY 2014 - 22:46 CET
The work of the high-speed railway line between Madrid and Barcelona ( 621 kilometers ) out to tender with a budget of 7,550 million euros and won by 6.822 million (down 9% ), but ended up costing 8.996 million ( 31 % more).
Among the award of the railway line and high-speed execution of work spent seven years plagued by incidents in the works and hundreds of modified than previously assumed by technicians ADIF ( the dependent Promoting public body) , they were raising budget well above the starting price set at the competition.
The Court of Auditors audited seven years (2002-2009) of contracts in this artwork , the layout of high speed highest budget implemented so far in Spain . The audit , completed last April, did not affect the total hiring , but a part that found that while the award is closed for less than 8.8% of the bid price , performance increased the final cost 43.2 % on the committed expenditure.
moreThe fiasco of the Andalusian AVE carried back hit 180 millionSpanish railway network and evolution of ratingProsecutors investigating cost overruns in the Pajares tunnelsDevelopment admits irregularities in three contracts AVEEvery kilometer AVE cost an average of 13.5 million euros
"All contracts ," the report of the Court of Auditors , " were initiated for reasons of urgency in order that it could meet the action program with the permission of the President of ADIF, by an abuse of competition that status of that body attached to its head . " These decisions about hiring works were reserved for the board of ADIF and the "urgency" that was claimed to to be the president who authorized the contracts " not been able to determine, since all of them were processed by the method short of open competition , without reduction of terms , "the Court of Auditors.
Public auditors note that during the execution of work in 356 major work contracts analyzed , where the price for which they were awarded the work increased " 69 amendments to contracts were signed ." Thus, one in five projects awarded price changed during implementation , raising the budget that was awarded .
Among the 69 changes identified by the Court of Auditors , the 14 additional works contracts and eight emergency works , "with price revisions and additional awards, bringing the total cost of the work originally contracted 3,035 million euros , representing an increase of 49.6 % " in the contracts examined by the Court of Auditors , an important part of the total.
Public auditors conclude that "the initial savings of 9.2% in the bid price of the contracts was eventually transformed into a cost overrun of 31% originally planned ." In addition to the extra cost , the works were not completed on time , with an average increase of 13.5 months the deadlines of contracts.
The Court of Auditors highlights a modified in Hospitalet -La Torrassa installment contract in which the price of award, a 221.6 % increased. In that contract , ADIF managed endorse the responsibility of what happened to the company and quantified damages for Administration euro 32 million when the ECA completed its work (ten months ago ) " there is no evidence that have been collected . "
The auditors said they "have identified numerous changes to projects that did not meet the legal requirements to qualify as new needs or unforeseen causes issues that already had knowledge before the start of construction and were due to defects or uncertainties project or omissions , or changes caused by coming of contracts by faulty construction execution . "
Setback auditor
The Court of Auditors recommended ADIF launch immediately a series of measures to avoid cost overruns and delays detected in the works of the AVE Madrid- Barcelona. These identified the following :
-New procedures that allow you to make a more realistic estimate of the time and cost of implementation; allocating more resources to previous research work during the drafting of the construction projects in order to prevent the widespread use of contract modifications .
- Spell out clearly in the records to authorize extensions of contracts and additional works the reasons on which these are based and avoid granting the extensions are motivated by reasons that justify them .
- Perform a more realistic estimate of the time required for the completion of the procedures for expropriation of land , so to reduce delays in the start of construction by the lack of availability of land .
AVEマドリード - バルセロナの監査人の監査報告書の裁判所
バルセロナへのAVEの作業は、6800万ドルを授与され、最終的には9000の費用がかかりました
621マイルは、最大9%が、売上高31%が割り当てられた
レポート状態を「多数の修正は、法的要件を満たしていない"
作品を膨張させるための逮捕ナインバルセロナ600万にAVE
フォトギャラリー逮捕TGVはバルセロナで動作
セットバック役
国マドリード5 MAY 2014 - 午後10時46分CET