スペイン政府は、海外投資銀行によるパナマ運河拡張工事のスペイン企業のSacyr会社への200'000'000$(2億$)の融資の条件の変更は、政府に追加負担をもたらさないと言明?
El Gobierno descarta que el cambio en el aval a Sacyr para el Canal eleve los costes
El consorcio reclama que el seguro de Cesce de 2009 se modifique para que sirva de aval
Sacyr retoma las obras de ampliación del Canal de Panamá
EP Madrid 20 FEB 2014 - 14:18 CET
The government ruled that the change in the support for Channel Sacyr raise costs
The consortium claims that insurance Cesce 2009 is modified to serve as a guarantee
Sacyr retakes works Panama Canal expansion
Madrid EP 20 FEB 2014 - 14:18 CET
The government ruled that changing conditions of public guarantee granted to Sacyr for the expansion project of the Panama Canal will be a higher cost to the public purse , and the same amount will remain (200 million dollars) and only modify the "object " of the guarantee .
This has been explained to government sources, after the information published Thursday by Reuters on amendment Cesce insurance , signed in 2009 and raised some questions to the Court of Auditors , that can serve as a financial guarantee for the construction Spanish .
This change would result in a requirement that the counter consortium for 400 million signed with Zurich also supports the new part of the funding to be obtained conglomerate after reaching an agreement with the Panama Canal Authority to resume works .
According to the Government , the change will not lead to a higher cost Cesce or to the public purse because only the object of the guarantee shall be amended to ensure not limited to companies not performing the work but to support the new resources they shall be obtained .