El Canal de Panamá asegura que pierde 300 millones de dólares por el retraso
La oposición considera una “vergüenza” el retraso en el proyecto de ampliación y arremete contra la empresa
Sacyr y Panamá llegan a un acuerdo
Alicia González Ciudad de Panamá 2 ABR 2014 - 18:49 CET
++++++++++++++++++++++++++++++++++++++++++++++++++++++
The Panama Canal says it loses $ 300 million for the delay
The opposition considers a "shame" the delay in the expansion project and the company blasts
Sacyr and Panama reach agreement
Alicia Gonzalez Panama City 2 ABR 2014 - 18:49 CET
The redevelopment of the Panama Canal , by a consortium led by the Spanish Sacyr, continue to generate controversy. Every year of delay in commissioning of the expansion the country loses $ 300 million ( 220 million euros). This has been assured by the administrator of the Panama Canal , Jorge Quijano , at the opening of the World Economic Forum held in the city of Panama . " Of course the delay in the works is an additional cost , since we already had the project was already run later this year. The estimated impact is about $ 300 million per year , "he claimed to the media.
moreThe Canal and the consortium signed the agreement to continue with the worksPastor and Minister of Foreign congratulate Panama CanalSacyr loses 496 million for the Panama Canal and VallehermosoPanama Sacyr and reach an agreement to resolve the crisis CanalSacyr resumes Canal works pending a final settlement
Following an agreement signed in March to resume the works to expand the Panama Canal , due to disagreements about the additional costs of the project, the Panama Canal Authority and the Grupo Unidos por el Canal ( UPC Group , a consortium of the Spanish Sacyr, the Impregilio Italian , Belgium's Jan de Nul and Panamanian Cusa ) pledged 100 million euros each to meet outstanding payments to suppliers and subcontractors . "It's contribution has already been made and it has been made $ 180 million that were outstanding . We are now finalizing the documents to include these documents in the contract , which will take several weeks yet , "claimed Quijano. From there , it will then Zurich insurer who must assess how it assumes its part of the agreement and disburses 400 million has been committed . The differences on the increased costs are ongoing in the court of arbitration, but Quijano said that the consortium has changed lawyers and have not taken new action.
The cessation of work has led to a significant delay in the time planned for the project implementation . According to the head of the Canal, the works are between 60% and 65% than it should according to the initial plans and hopes that can recover the full pace of work in about a month .
" The delay in the completion of the works is a shame."
Juan Carlos Navarro , leader of the Democratic Revolutionary Party
The controversy over the expansion of the Canal has fully entered electoral campaign. The opposition leader , Juan Carlos Navarro, the Democratic Revolutionary Party (PRD ) , said that if he wins the presidential election next May 4 his government will make the completion of the works their number one priority . " The delay in the completion of the works is a shame. That happens when you hire a company in financial difficulties and there we can see the results. Our priority will be to complete the works with the highest quality standards , do it sooner rather than later and , if possible , without increasing the expected cost of the work " , said during his speech at the World Economic Forum .